NAHB Model Green Home Building Guidelines Checklist

For more information on building or a free consultation CONTACT US

NAHB Model Green Home Building Guidelines Checklist

The NAHB National Green Building Program helps any builder, anywhere build a green home. When you attend the NAHB National Green Building Conference, work toward your Certified Green Professional™ educational designation or plan the green features in your next project using the online scoring tool at nahbgreen.org, you're part of the program.

You can score your home using the NAHB Model Green Home Building Guidelines, the first national rating system for green, single-family homes. The online scoring tool, an explanation of the point system, information on how to score your project to the Bronze, Silver or Gold level and a list of accredited verifiers are all available at nahbgreen.org.

This score sheet will introduce you to the rating system.
1.1 Select the site to minimize environmental impact
1.1.1 ___ 7 pts. Avoid environmentally sensitive areas identified through site Footprinting process

1.1.2 ___ 9 pts. Choose and infill site

1.1.3 ___ 7pts. Choose a greyfield site

1.1.4 ___ 7 pts. Choose an EPA-recognized brownfield site

1.2 Identify goals with your team
1.2.1 ___ 6 pts. Establish a knowledgeable team by identifying team member roles and writing a Mission Statement that includes project goals and objectives.

1.3 Design the site to minimize environmental impact and protect, restore, and enhance the natural features and environmental qualities of the site.
1.3.1 ___ 6 pts. Conserve natural resources

1.3.2 ___ 6 pts. Site the home and other built features to optimize solar resource

1.3.3 ___ 5 pts. Minimize slope disturbance

1.3.4 ___ 6 pts. Minimize soil disturbance and erosion

1.3.5 ___ 8 pts. Manage storm water using low impact development

1.3.6 ___ 8 pts. Devise landscape plans to limit water and energy demand

1.3.7 ___ 5 pts. Maintain wildlife habitat

1.4 Develop the site to minimize environmental intrusion during onsite construction

1.4.1 ___ 5 pts. Provide onsite supervision and coordination during clearing, grading, trenching,
paving, to ensure targeted green development practices are implemented

1.4.2 ___ 5 pts. Conserve existing onsite vegetation

1.4.3 ___ 6 pts. Minimize onsite soil disturbance and erosion

1.5 Innovative Options
1.5.1 ___ 6 pts. Share driveways or parking

Section Total ______

Section 2: Resource Efficiency

2.1 Reduce the quantity of materials used and waste generated

2.1.1 ___ 3 pts. Create an efficient floor plan that maintains home's functionality

2.1.2 ____8 pts. Employ advanced framing techniques

2.1.3 ___ 6 pts. Use building layouts that maximize resources and minimize material cuts

2.1.4 ___ 7 pts. Create a detailed framing plan and material takeoffs

2.1.5 ___ 4 pts. Use materials requiring no additional finish resources to complete application on site

2.1.6 Use pre-cut or pre-assembled building systems or methods as outlined below:

___3 pts./per Provide pre-cut joists or pre-manufactured floor truss

___ 6 pts. Provide panelized wall framing system

___ 6 pts. Provide panelized roof framing system

___ 7 pts. Provide modular construction for entire house

2.1.7 ___ 4 pts. Use a frost-protected shallow foundation

2.2 Enhance durability and reduce maintenance
2.2.1 ___ 6 pts. Provide covered entry (awning, covered porch) at exterior doors

2.2.2 ___ 7 pts. Use recommended-sized roof overhangs for the climate

2.2.3 ___ 7 pts. Install perimeter drain for all basement footings sloped to discharge to daylight, sump pit

2.2.4 ___ 6 pts. Install drip edge at eave and gable roof edges

2.2.5 ___ 6 pts. Install gutter and downspout system to divert water 5 feet away from foundation

2.2.6 ___ 7 pts. Divert surface water from all sides of building

2.2.7 ___ 7 pts. Install continuous and physical foundation termite barrier where necessary

2.2.8 ___ 7 pts. Use termite-resistant materials for walls, floor joists, trusses, exterior decks, etc.

2.2.9 ___ 8 pts. Provide a water-resistant barrier behind the exterior veneer or siding

2.2.10 ___ 5 pts. Install ice flashing at roof edge

2.2.11 ___ 7 pts. Install enhanced foundation waterproofing

2.2.12 ___ 9 pts. Employ and show on plans all flashing detail

2.3 Reuse materials
2.3.1 ___ 6 pts. Disassemble existing buildings instead of demolishing

2.3.2 ___ 5 pts. Reuse salvaged materials

2.3.3 ___ 6 pts. Provide onsite bins or space to sort, store scrap materials

2.4 Recycled content materials
2.4.1 ___ 3 pts. Use recycled-content building materials. List components used

2.5 Recycle waste materials during construction
2.5.1 ___ 7 pts. Develop and implement a construction and demolition waste management plan

2.5.2 ___ 5 pts. Conduct onsite recycling efforts

2.5.3 ___ 6 pts. Recycle construction waste offsite

2.6 Use renewable materials
2.6.1 ___ 3-5 pts. Use materials manufactured from renewable resources

2.6.2 ___ 4pts./per Use certified wood and use wood-based materials from certified sources

2.7 Use resource-efficient materials
2.7.1 ___ 3 pts. Use products that are composed of fewer resources

2.8 Innovative Options
2.8.1 ___ 5 pts. Use locally available, indigenous materials

2.8.2 ___ 8 pts. Employ a life-cycle assessment tool to choose environmentally preferable products.

Section Total _____

Section 3: Energy Efficiency
3.1 Minimum Energy Efficiency Requirements

3.1.1 Mandatory Home is equivalent to the IECC 2003 or local energy code, whichever is more stringent

3.1.2 Mandatory Size space heating and cooling system and equipment according to building heating and cooling loads calculated using ANSI/ACCA Manual J 8th edition or equivalent

3.1.3 Mandatory Conduct third party plan review to verify design/compliance with Energy Efficiency section

3.2 Performance Path
3.2.1 Home is X% above IECC 2003

___ 37pts. 15% (Bronze)

___ 62 pts. 30% (Silver)

___ 100 pts. 40% (Gold)

3.3 Prescriptive Path
An energy-efficiency practice identified with a "(PP)" in Section 3.3 is a Performance Path practice likely to be used to calculate X% above ICC IECC in Section 3.2. If Section 3.3 is used to obtain points in addition to points from 3.2, those practices from Section 3.3 used to comply with Section 3.2 shall not be awarded any additional points.

3.3.1 Building Envelope
Increase in effective R-value of building envelope using advanced framing techniques, continuous insulation, and/or integrated structural insulating system. Measures may include but are not limited to:
A.(PP) ___ 8 pts. SIP, or

___ 8 pts. ICF, or

___ 6 pts. Advanced framing or insulated corners, intersections and headers

___ 2 pts. Raised heel trusses

___ 4 pts. Continuous insulation on exterior wall

___ 4 pts. Continuous insulation on cathedral ceiling

B.(PP) ___ 10 pts. Air sealing package is implemented to reduce infiltration

C.(PP) ___ 8 pts. ENERGY STAR®-rated windows appropriate for the local climate

3.3.2 HVAC design, equipment, and installation
A. ___ 8 pts. Size, design, and install duct system using ANSI/ACCA Manual D® or equivalent

B. ___ 8 pts. Design radiant/hydronic space heating system using industry-approved guidelines

C. ___ 8 pts. Use ANSI/ACCA Manual S® or equivalent to select heating and cooling equipment

D. ___ 8 pts. Verify performance of the heating and cooling system

E. ___ 6 pts. Use HVAC installer or technician certified by national or regionally recognized program

F.(PP) Fuel-fired space heating equipment efficiency (AFUE)

___ 4 pts. Gas furnace > 81%

___ 6 pts. Gas furnace > 88% (ENERGY STAR)

___ 8 pts. Gas furnace > 94%

___ 2 pts. Oil furnace > 83%

___ 2 pts. Gas or oil boiler > 85% (ENERGY STAR)

___ 6 pts. Gas or oil boiler > 90%

G.(PP) Heat pump efficiency (cooling mode)

___ 6pts. SEER 13-14

___ 6 pts. SEER 15-18

___ 7 pts. SEER 19+

___ 9 pts. Staged air conditioning equipment

H.(PP) Heat pump efficiency (heating mode)

___ 6pts. 7.2 - 7.9 HSPF

___ 7 pts. 8.0 - 8.9 HSPF

___ 9 pts. 9.0 - 10.5 HSPF

___ 10 pts. > 10.5 HSPF

Note: Split systems must be ARI-tested as a matched set.

I.(PP) Ground source heat pump installed by certified geothermal service contractor (cooling mode)
___ 5 pts. EER = 13-14

___ 6 pts. EER = 15-18

___ 8 pts. EER = 19-24

___ 10 pts. EER = >25

Note: For Sections A-F and I, add 3 points if Manuals S and D and start-up procedures
are followed when units are installed.

J.(PP) Ground source heat pump installed by a certified geothermal service contractor (heating mode)

___ 6 pts. COP 2.4 -2.6

___ 8 pts. COP 2.7 - 2.9

___ 10 pts. COP > 3.0

K. ___ 6 pts. Seal ducts, plenums, equipment to reduce leakage. Use UL 181 foil tapes and/or mastic

L. ___ 8 pts. When installing ductwork:

1. Do not use building cavities used as ductwork, e.g., panning joist or stud cavities

2. Install all heating and cooling ducts and mechanical equipment within conditioned
Envelope

3. Do not install ductwork in exterior walls

M. ___ 6 pts. Install return ducts/transfer grilles in rooms with doors (except baths, kitchens, closets, laundry)

N. ___ 1 pt./per Install ENERGY STAR-rated ceiling fans

O. ___ 4 pts. Install whole-house fan with insulated louvers

P. ___ 8 pts. Install ENERGY STAR-labeled mechanical exhaust for every bathroom ducted to
Outside

3.3.3 Water heating, design, equipment, and installation
A. ___ 4 pts. Water heater Energy Factor equal to or greater than those listed

Natural Gas:
30 gallons/ 0.64 Energy Factor

40gallons/ 0.62 Energy Factor

50 gallons/ 0.60 Energy Factor

65 gallons/ 0.58 Energy Factor

75 gallons/ 0.56 Energy Factor

Electric:
30 gallons/ 0.95 Energy Factor

40 gallons/ 0.94 Energy Factor

50 gallons/ 0.92 Energy Factor

65 gallons/ 0.90 Energy Factor

80 gallons/ 0.88 Energy Factor

100 gallons/ 0.86 Energy Factor

Oil:
30 gallons/ 0.59 Energy Factor

50 gallons/ 0.55 Energy Factor

B. ___ 4 Ipts. nstall whole house instantaneous (tankless) water heater

C. ___ 4 pts. Insulate all hot water lines with a minimum of 1" insulation

D. ___ 3 pts. Install heat trap on cold and hot water lines to and from the water heater

E. ___ 5 pts. Install manifold plumbing system (parallel piping configuration, stacking plumbing)

3.3.4 Lighting and appliances

A. ___ 7 pts. Use and ENERGY STAR Advanced Lighting Package

B. ___ 7 pts. Install all recessed fixtures within the conditioned envelope

C. ___ 7 pts. Install motion sensors on outdoor lighting

D. ___ 2 pts. Install tubular skylights in rooms without windows

E. Install ENERGY STAR-labeled appliance

___ 3 pts. Refrigerator

___ 3 pts. Dishwasher

___ 5 pts. Washing machine

3.3.5 Renewable energy/solar heating and cooling

3.3.5.1 Solar space heating and cooling (See Guidelines for details)

A. ___ 10 pts. Use sun-tempered design: building orientation, sizing of glazing, design of overhangs to provide shading

B. ___ 10 pts. Use passive solar design: sun-tempered design as above plus additional southfacing glazing, appropriately

C. ___ 8 pts. Use passive cooling, including shading, overhangs, window cross ventilation

3.3.5.2 Solar water heating

A. Install SRCC-rated solar water heating system

___ 8 pts. Solar fraction: 0.3

___ 10 pts. Solar fraction: > 0.5

3.3.5.3 Additional renewable energy options

A. Supply electricity needs by onsite renewable energy source whereby the system is estimated to produce the following kWh per year:

___ 8 pts. 2,000 - 3,999

___ 10 pts. 4,000 - 5,999

___ 12 pts. 6,000+

B. Provide clear and unshaded roof area (+/- 30 degrees of south or flat, minimum 200 square feet) for future solar collector or photovoltaics. Provide rough-in piping from the roof to the utility area

___ 3 pts. Conduit

___ 5 pts. Insulated piping

C. _____ 2 Provide homeowner with information and enrollment materials about options to
purchase green power from the local electric utility

3.3.6 Verification

3.3.6.1 ___ 8 pts. Conduct onsite third-party inspection to verify installation of energy-related features

3.3.6.2 ___8pts./per Conduct third-party testing to verify performance: blower door, duct leakage, flow rates

3.3.7 Innovative Options
A. ___ 2 pts. Install drainwater heat-recovery system

B. ___ 6 pts. Install de-superheater in conjunction with ground-source heat pump

C. ___ 6 pts. Install heat pump water heater rated to current DOE test standard and with EF > 1.7

Section Total _____

Section 4: Water Efficiency
4.1 Water Use

4.1.1 ___ 6pts./per Hot water delivery to remote locations aided by installation of:

A. On-demand water heater at point of use served by cold water only

B. Control-activated recirculation system

4.1.2 ___ 9 pts. Water heater located within 30 feet pipe run of all bathrooms and kitchen

4.1.3 ___ 7pts./per ENERGY STAR water-conserving dishwasher, washing machine, etc.

4.1.4 ___ 2pts./per Water-efficient showerhead using aerator/venturi with flow rate < 2.5 gpm

4.1.5 ___ 2pts./per Water-efficient sink faucets/aerators < 2.2 gpm

4.1.6 ___ 4-6 pts. Ultra low flow (<1.6 gmp/flush) toilets: (power-assist: 4 pts; dual flush: 6 pts.)

4.1.7 ___ 7 pts. Low-volume, non-spray irrigation system installed such as drip irrigation, bubblers, etc.

4.1.8 ___ 6 pts. Irrigation system zoned separately for turf and bedding areas

4.1.9 ___ 7 pts. Weather-based irrigation controllers such as computer-based weather record

4.1.10 ___ 9 pts. Collect and use rainwater, as permitted by local code

4.1.11 ___ 7 pts. Innovative wastewater technology as permitted by local code

4.2 Innovative Options
4.2.1 ___ 6 pts. Shut-off valve, motion sensor, or pedal-activated faucet for intermittent on/off operation

4.2.2 ___ 6 pts. Separate and re-use greywater as permitted by local code

4.2.3 ___ 6 pts. Composting or waterless toilet as permitted by local code

Section Total _____

Section 5: Indoor Environmental Quality
5.1 Minimize potential sources of pollutants

5.1.1 ___ 8 pts. For vented space heating and water heating equipment:

A. Install direct vent equipment

B. Install induced/mechanical draft combustion equipment

5.1.2 ___ 6 pts. Install space heating and water heating equipment in isolated mechanical room or closet with an outdoor source of combustion and ventilation air

5.1.3 ___ 6 pts. Install direct-vent, sealed-combustion gas fireplace, sealed wood fireplace, or sealed woodstove or install no fireplace or woodstove

5.1.4 ___ 9 pts. Ensure a tightly-sealed door between the garage and living area and provide continuous air barrier between garage and living areas including air sealing penetrations

5.1.5 ___ 6 pts. Ensure particleboard, medium density fiberboard (MDF and hardwood plywood
substrates are certified to low formaldehyde emission standards

5.1.6 ___ 5 pts. Install carpet, carpet pad, and floor covering adhesives that hold "Green Label" from Carpet and Rug Institute's indoor air quality testing program or equivalent

5.1.7 ___ 5 pts. Mask HVAC outlets during construction and vacuum all ducts, boots and grills

5.1.8 ___ 3 pts. Use Low-VOC emitting wallpaper

5.2 Manage potential pollutants generated in the home

5.2.1 ___ 7 pts. Vent kitchen range exhaust to the outside

5.2.2 Provide mechanical ventilation at a rate of 7.5 cfm per bedroom +7.5 cfm and controlled automatically or continuous with manual override. Choose:

___ 7 pts. Exhaust or supply fan(s)

___ 9 pts. Balanced exhaust and supply fans

___ 10 pts. Heat-recovery ventilator

___ 10 pts. Energy-recovery ventilator

5.2.3 ___ 3 pts. Install MERV 9 filters on central air or ventilation systems

5.2.4 ___ 4 pts. Install humidistat to control whole-house humidification system

5.2.5 ____ 6 pts. Install sub-slab depressurization system to facilitate future radon mitigation system

5.2.6 ___ 9 pts. Verify all exhaust flows meet design specifications

5.3 Manage moisture (vapor, rainwater, plumbing, HVAC)
5.3.1 ___ 6 pts. Control bathroom exhaust fan with a timer or humidistat

5.3.2 ___ 6 pts. Install moisture-resistant backerboard under tiled surfaces in wet areas

5.3.3 ___ 9 pts. Install vapor retarder directly under slab (6-mil) or on crawl space floor (8-mil)

5.3.4 ___ 6 pts. Protect unused moisture-sensitive materials by just-in-time delivery, storing in dry area, or tenting and storing on raised platform

5.3.5 ___ 5 pts. Keep plumbing supply lines out of exterior walls

5.3.6 ___ 4 pts. Insulate cold water pipes in unconditioned spaces

5.3.7 ___ 4 pts. Insulate HVAC ducts, plenums and trunks in unconditioned basements and crawl spaces

5.3.8 ___ 4 pts. Check moisture content of wood before it is enclosed on both sides

Section Total _____

Section 6: Operation, Maintenance, and Homeowner Education
6.1 ___ 9 pts. Provide Home Manual to owners/occupants on the use and care of the home
(See Guidelines for details)

6.2 ___ 2 pts. Include optional information in the Home Manual. (See Guidelines for details.)

6.3 ___ 7 pts. Provide education to owners/occupants in the use and care of their dwellings: Instruct Homeowner/occupants about the building's goals and strategies and occupant's impact on costs of operating the building. Provide training to owners/occupants for all control
systems in the house.

6.4 ___ 1 pt. Solid waste: Encourage homeowners/occupants

Section Total _____

Section 7: Global Impact
7.1 Products

7.1.1 ___ 3 pts. Note product manufacturer's operations and practices (environmental management system)

7.1.2 ___ 6 pts. Choose low- or no- VOC indoor paints

7.1.3 ___ 5 pts. Use low-VOC sealants

7.2 Innovative Options
7.2.1 ___ 4 pts. Demonstrate that builder's operations and practices include environmental management system concepts

There's More to NAHB Green.
This checklist is only a summary and omits pertinent information related to the compliance and verification. Further information about the intent of the prescriptions herein and how they are verified for certification purposes can be found at nahbgreen.org. Any questions related to the compliance should be directed to your chosen certification verifier or the NAHB Research Center.

Using the online version of this scoring tool at nahbgreen.org as a guide, a builder can request the home receive National Green Building Certification from the NAHB Research Center. The home must be inspected at close-in and when it is finished to verify that the green features chosen are in place.

NAHB Green also includes marketing and advocacy guidance for members and local home building associations to communicate the benefits of green building and the importance of keeping these innovative practices voluntary. HBAs can affiliate with NAHB Green in addition to maintaining current local or regional certifications.

Learn more at
www.nahbgreen.org
It's green building, priced right

Mountain Construction does custom home building in any building style, including conventional new homes, remodeling and restorations, log and timber frame home and structural insulated panel homes. Check out our site and learn more about Log Home Building as well as our Construction and Remodeling services.

 

See more photos of our work.